SUPERBONUS 110% MARINE RESORT COMPLEX
General Data
- Location: Viale Giuseppe Carducci, 181 – CESENATICO (FC)
- Reference year: 2024
- Work start date: 01/11/2024
- Duration of work: 426 days
- Work amount: <TAG1> 8,247,424
- Average working presence: 20 workers a day
Location — Cesenatico (FC)
The project concerns energy efficiency and seismic improvement of a historic building known as Agip Marine Colony, built between 1936 and 1938 and characterised by an architectural mix between tradition and innovation. The work is an example of an intervention on a historic building with the aim of architectural and technological valorization.
Design and Technological Choices
The project preserved the original structure by focusing on energy efficiency and seismic improvement, integrating structural consolidation interventions with respect for architectural identity and visual impact.